HEWLETT PACKARD
CASE STUDY

PE appointed Backbone to deliver the full,
end-to-end design and build scope, for their
consolidated and refurbished premises on
Autumn Street off Rivonia Road.

CONCEPT PHASE

  • Backbone Management was appointed by HPE as Full-Turn-key Management Agent for the reinstatement, consolidation and refurbishment of their current office premises and the return of unused office to the Landlord for new tenants. This function included all design, procurement and delivery of the office space within a live and operational office environment in 2 phases.
  • The Client also had the duty to re-instate old tenancy area for the landlord due to the down-sizing and consolidation. This had to be done in time for the new tenants to start a new fit-out.

RENDER PHASE

  • Build and fit out duration of 5 months split over 2 phases.
  • The client moved into their new space on time, under budget.
  • The Landlord received their new tenancy areas in time to start the new projects.

FINAL PHASE

INDUSTRY

  • Global Technology Services

GEOGRAPHY

  • Rivonia, Johannesburg
  • Fit-out Duration 5 Months
  • Description Fit-Out 2,000m2 Office

SERVICES PROVIDED

  • Project and Cost